Draft Version 1.1 Minutes of the 3rd ESEAS-RI Project Team Meeting

Place: Ardilaun House Hotel, Galway, Ireland
Date: 13-14 May 2004




Minutes written by Hans-Peter Plag (Version of 20 May 2004).

Participants:


Hans-Peter Plag (HPP), NMA, (Coordinator, Task leader 2.4)
Per Knudsen (PK), KMS, (WP3 leader)
Dov Rosen (DR), IOLR, (WP4 leader)
Richard Bingley (RB), UNOTT, (WP2 leader, Task leader 1.1 + 2.8)
Lesley J. Rickards (LJR), NERC-POL, (WP1 leader)
Bente Lilja Bye (BLB), NMA
Alan Edwards (AE), EC


Agenda:

  1    Welcome and Introduction
  2    Discussion of the Agenda
  3    Announcement from the Coordinator
  4    Report from the Coordinator
  5    Reports from the WP leaders and discussions
  5.1  Lesley Rickards reports on WP1
  5.2  Richard Bingley reports on WP2
  5.3  Per Knudsen reports on WP3
  5.4  Dov Rosen and Hans-Peter Plag report on WP4
  6    Summary of the status, deviations, and necessary actions
  7    Management report
  7.1  Hans-Peter Plag: Presentation of the draft report
  7.2  Discussion and finalising of the report (all)
  8    Technical Implementation Plan (TIP)
  9    External Reviewing
  10   The ESEAS Meetings in November 2004: Programme, web pages, invited speakers
  11   Publications
  12   Future proposals
  13   The next phase of the ESEAS
  13.1 The assessment report
  13.2 Next ESEAS GB meeting
  13.3 Merging ESEAS and MedGLOSS
  14   ESEAS/GLOSS and GMES/GEO
  15   List of Action Items
  16   Any Other Business (AOB)
  17   Date and place of next meeting
1 Welcome and Introduction

Hans-Peter Plag welcomed all participants and in particular Alan Edwards as representative of the European Commission.

2 Discussion of the Agenda

The agenda was accepted as proposed. However, since Alan Edwards had to leave at lunch time on 14 May, the topics 12 and 14 were discussed after Topic 6.

3 Announcement from the Coordinator

Hans-Peter Plag informed the participants that he has accepted a position at the Nevada Bureau of Mines, University of Nevada, Reno, USA. Most likely, he will be leaving NMA in July. However, it is expected that he will be able to contribute to the ESEAS Workshop in November.

Proposed new coordinator is Bente Lilja Bye , who works at NMA. Bente Lilja Bye Bente Lilja Bye is senior adviser to the Director of the Geodetic Institute of NMA. She is also the Research coordinator for NMA. She holds an advanced degree in Theoretical Astrophysics from University of Oslo in 1990. She worked at the Research Council of Norway for a decade with responsibilities such as Material Sciences, International Research Cooperation within Science and Technology, national coordination of COST activities. She has long experience in evaluating research projects and developing both national and international research policies and strategies. From 1995-2000 she was Managing Director of Norwegian Synchrotron Research AS, which she also was instrumental in establishing. Ms Bye has been a member of several international committees such as member of COST CSO, vice chair of Administrative and Finance Committee of European Synchrotron Research Facility, the Steering Committee of the Swiss-Norwegian Beamline and others. From 2001-2002 Ms Bye was Managing Director of an IT-company with HQ in Norway and numerous subsidiaries in Northern Europe and Asia.

Alan Edwards explained that in order to have the new coordinator accepted by the Commission, the consortium needs to agree on the person. Formally, only the first two pages of the CPF need to be updated, signed and sent to the Commission. In a covering letter, the approval of all partners needs to be indicated.

Action Item PT-3-1: Hans-Peter Plag to ask the consortium for agreement to have Bente Lilja Bye as new coordinator. Responsible: Hans-Peter Plag, Deadline: 30 June 2004.

Alan Edwards informed that he most likely has to step down as responsible officer for ESEAS. Gilles Ollier will take over. He has a background in marine science and strongly advocates the research in that field.

4 Report from the Coordinator

Hans-Peter Plag reported on the activities in the last six months (see ppt ). With respect to the reporting related to the first year, he reported that the first annual report was submitted and this report is accepted by the Commission. Moreover, the cost statements are also to a large extent accepted. Some partners have significantly under-spent compared to the plan, while a few partners have nearly spent their resources after Year 2. In the latter case, a re-allocation of funds may be necessary after the second year.

Concerning activities in the reporting period, the coordinator mentioned that there have been two WP meetings, namely a WP1/WP3 meeting in January 2004 in Darmstadt, and a WP2/WP4 in February in Madrid. The ESEAS has a good chance of being registered as a service under the GMES umbrella.

With respect to presentations at meetings, the coordinator mentioned that the ESEAS was asked to give a presentation at the 4-th GMES Forum in November 2003 in Baveno, Italy, with the focus on the view of ESEAS as a non-governmental organisation on GMES. The ESEAS-RI project, and partiularly the status of WP2, was reported at the EUREF TWG meeting in March 2004 in Budapest. Moreover, the project was also presented as a poster at the Euroocean 2004 in Galway, Ireland.

Concerning the personnell at the ESEAS CB, Hans-Peter Plag reported that the project manager, Hanne Heiberg, left on 7 May 2004. The position was announced and selection is currently under way.

With respect to the IGS TIGA project, the coordinator could report that in the frame of ESEAS-RI WP2, a good cooperation has developed.

Hans-Peter Plag commented on the status of a few selceted AIs from previous meetings. With respect to

Action Item PT-2-33: All partners to provide references to presentations and publications for Section 2 of the Annual Report. Responsible: all Deadline: 20 Nov 2003.

and

Action Item PT-2-34: All partners to provide posters and presentations to the ESEAS CB for inclusion on eseas.org. Responsible: all Deadline: open.

he pointed out that certainly not all papers, posters and presentations related to ESEAS and ESEAS-RI have been reported. He urged the WP leaders to push WP members to contribute to the list.

Concerning

Action Item PT-2-35: Hans-Peter Plag to inform everybody about the requirements for documentation of who worked when on the project. Responsible: Hans-Peter Plag, Deadline: 30 November 2003.

he used the opportunity to ask Alan Edwards for comments related to the required documentation. Alan Edwards emphasised that some kind of a certification system needs to be in place to document that Mr. X or Mrs. Y have worked so many hours for ESEAS-RI. This information needs to be certified by someone outside of the project, e.g. a financial manager. The certification is very important. Certification has to come from a person on a level high enough to approve the correctness of the hours registered. In some cases, the administrative responsible given on the CPF may be the right person for the certification, but not in all cases. Certification should be on a weekly, monthly or, exceptionally, three monthly basis. Records of the hours spent have to be kept at the respective institute. Importantly, this also applies to those persons not being funded by the EC, that is, the work done by those in AC partners that are not directly paid by the project.

These requirements concern the internal systems used at each participating institution for registering human resources and certifying that these are actually used on the project. This is not covered by the annual cost statements. This is similar to the demand that all invoices for durable equipment or all travel claims need to be kept internally for later audits. The acceptance of the cost statement by Commission does not imply that there cannot be an audit where all costs have to be documented in a proper way. Thus, the requirement for documenting human resources in a proper way is not different from all other requirements for the internal accounting system. In other words, participation in a EU project requries that the partner has an internal system for accounting that also includes registering and certifying human resources, which can be checked in case of an audit.

In case of an audit, the lack of certified information about the person resources used on the project is most often what causes severe problems. The other main cause is due to durable equipment being messed up.

Action Item PT-3-2: Hans-Peter Plag to inform the consortium about the requirements for documentation of human resources spend on the project. Responsible: Hans-Peter Plag, Deadline: 20 May 2004.

Rational: There are clear requirements for documentation of human resources used in the project. These need to be followed in order to avoid problems during audits.

Hans-Peter Plag also addressed

Action Item WP4-2-12: All those who are responsible for an upgraded tide gauge to provide information about data upload to the ESEAS DS (latency, start date, rate) or about the server to down-load data from (IP address, access, latency, start date, rate). Responsible: ALL, Deadline: 28 February 2004.

and complained that the coordinator/ESEAS CB up to now did not receive sufficient information from the partners.

5 Reports from the WP leaders and discussions

5.1 Lesley Rickards reports on WP1

Lesley J. Rickards presented the status of WP1 (see ppt ).

Concerning T1.1, it needs to be checked which sites in the list are actually on the ESEAS map and which should be on the new ESEAS clickable map. Richard Bingley informed that he updated the list twice but not sent it to the CB. This will be done soon.

Concerning T1.2, fragmentation of quality control between the different institutes is still a problem though some progress has been made. The ESEAS Quality Control Software package will be an important contribution to European wide standardisation.

The revised version of the deliverable document is with Begona Perez Gomez and Maria-Jesus Garcia for final corrections:

Action Item PT-3-16: Lesley J. Rickards to ensure that the quality control document is finalised and made available on the delivery page. Responsible: Lesley J. Rickards, Deadline: 30 June 2004.

Rational: According to AI PT-2-3, the document was supposed to be available in Nov. 2003. It now needs to be made available a.s.a.p.

The availability of quality control software was discussed. It was suggested to make a standard package compliant with the ESEAS Quality Control document available, e.g. for down-load from the ESEAS web page. Moreover, in the future a centralised quality control on the ESEAS Data Server needs to be made available. Otherwise, a homogeneous ESEAS data quality cannot be ensured:

Action Item PT-3-17: Lesley J. Rickards to ensure together with the T1.2 members and the whole ESEAS consortium that a standard ESEAS Quality Control software is defined and that the programs are made available for down-load on the ESEAS Web server. Responsible: Lesley J. Rickards, Deadline: 30 June 2004.

Rational: A standard software package for quality control compliant to the quality control document is a necessary step towards a homogeneous ESEAS data quality. Initially, the software is made available for down-load. However, a next step should be to have the software installed on the ESEAS Data Server.

T1.4 is in a good shape and some charts have already been digitised and quality control (T1.5) has started. The tasks 1.4. and 1.5 have high priority during the remainder of the ESEAS-RI project.

Concerning T1.3, Hans-Peter Plag reported that there is a serious delay. The delay is due mainly due to the fact that the data portal is developed under six demanding principles (see also ppt ), while at the same time the resources at NMA are limited. He also presented some initial thoughts with respect to a global datanet, which would solve many of the problems inherent in the current approaches. There was considerable discussion concerning the global datanet. Alan Edwards pointed out that the system sketched by Hans-Peter Plag is not in disagreement with the thoughts and ideas developed in the frame of GMES.

It was strongly emphasised that the ESEAS Data Portal needs to be operational a.s.a.p. A meeting of T1.3 contributers is needed in early June in order to distribute the work for the DP and to get the web page established. Alan Edwards pointed out that from his point of view, the deadline for the web page to be up is end of September, in order to be able to report in the second annual report and the November workshop:

Action Item PT-3-3: Hans-Peter Plag to call for a Task 1.3 meeting in order to consolidate the development of the ESEAS Data Portal. Responsible: Hans-Peter Plag, Deadline: 20 May 2004.

Rational: The ESEAS Data Portal needs urgently be established and therefore, the current bottleneck due to a lack of resources at NMA needs to be eliminated. This requires input from all ESEAS-RI partners who have the right expertise. The meeting should take place in June with the goal to get the DP opeartional by September.

The sea-level related information on the ESEAS web page needs to be boosted and improved. This needs to be a join effort of the ESEAS community:

Action Item PT-3-4: Hans-Peter Plag to ask the ESEAS community to provide information for the ESEAS web page "About Sea Level". Responsible: Hans-Peter Plag, Deadline: 20 May 2004.

Rational: The ESEAS web page should be an information source for sea level. Currently, very little is available of interest for non-scientific users. This is a major deficit of ESEAS, which can fairly easily be corrected.

5.2 Richard Bingley reports on WP2

Richard Bingley gave an overview of WP2 and discussed the status of the work (see pdf ). The WP is largely in line with the DoW. The strategy documents produced in T2.1 and T2.2 will be updated according to input from T2.3, T2.4, and T2.5.

In the frame of T2.3, the next step of the intercomparison of the analysis methods and ACs has been completed. The results of longer time series computed with the different methods show relatively large discrepancies, which require further investigations (see pdf ). In particular, using the IGS orbits and clocks for precise point positioning does not results in reasonable trends. Bernese in precise point positining mode also gives time series with unreasonable trends.

For T2.4, Hans-Peter Plag reported on the status of the SBL (see respective pages in ppt ). There, global grids of 3-d displacements are available but currently no time series for the ESEAS CGPS sites. NMA needs to provide the time series for the EOS with co-located GPS:

Action Item PT-3-5: Halfdan Pascal Kierulf to provide the time series of displacement due to air pressure loading for all ESEAS CGPS sites. Responsible: Halfdan Pascal Kierulf, Deadline: 30 June 2004.

Concerning the WP2 AIs, Richard Bingley discussed the status on the basis of the table provided in the rtf file .

It was noted that the two AIs

Action Item WP2-3-4: Hans-Peter Plag to send out the Master files for GPS site documentation to the GPS analysis groups for comments. Responsible: Hans-Peter Plag, Deadline: 28 February 2004.

and

Action Item WP2-3-5: Halfdan Pascal Kierulf to send out the ESEAS Time series files for comments. Responsible: Halfdan Pascal Kierulf, Deadline: 28 February 2004.

are still open and it was emphasised that these AIs need to be addressed soon.

5.3 Per Knudsen reports on WP3

Per Knudsen gave an overview of the status of WP3 (see pdf ). T3.1 resulted in very good results and the report is available on the ESEAS Status Web Page. The initial comparison of the softwares used by the contributers revealed significant discrepancies which could be reconciled. Globally, the interannual spectrum of sea level does not exhibit any significant and persistent frequencies but regionally, spatially consistent variations are found. However, these variation change with time and this makes the propagation back in time more difficult, if not impossible.

T3.2 was supposed to end by April 2004 and most of the work is done. The EOF are available.

T3.3 started and is looking at the interdecadal variations, which is a rather difficult task due to the small number of long tide gauge records available and due to the nature of the sea level variations.

The correlations indicate some large scale tele-connection. However, it is not clear whether these are stable in time.

Hans-Peter Plag suggested to have a workshop to do brain-storming in order to see how to go on with T3.3:

Action Item PT-3-6: Per Knudsen together with Hans-Peter Plag to organise a Task 3.3 meeting in June in order to assess the results of T3.1 and T3.2 and to decide how to solve T3.3. Responsible: Per Knudsen, Deadline: 20 May 2004.

Since Hans-Peter Plag , who is task leader for T3.4 is leaving, a new task leader is required. As new task leader for T3.4, Mikis Tsimplis was suggested by Hans-Peter Plag .

Action Item PT-3-7: Per Knudsen to clarify whether Mikis Tsimplis can take the leadership for T3.4. Responsible: Per Knudsen, Deadline: 20 May 2004.

5.4 Dov Rosen and Hans-Peter Plag report on WP4

Dov Rosen reported the status of WP4 (see pdf ). T4.1 is in a good shape and has produced significant results.

For T4.2, it is important to start the data delivery to the ESEAS Data Server. With respect to T4.3, it was emphasised that the remaining CGPS sites have to be made operational a.s.a.p. It was pointed out that the delay in setting up the sites is solely the responsibility of the respective partners. Problems due to bureaucratic procedures, late purchase or site selection cannot be used as an explanation. All these reasons are due to poor preparation of the work. This view was confirmed by Alan Edwards . The following AIs were agreed:

Action Item PT-3-8: Hans-Peter Plag to contact Maria-Jesus Garcia and to clarify the status of the CGPS receiver, which is supposed to deliver data since early April. Responsible: Hans-Peter Plag, Deadline: 20 May 2004.

Action Item PT-3-9: Hans-Peter Plag to contact all partners with pending CGPS installation and to urge them to progress as soon as possible since otherwise their installation may not be useable for ESEAS-RI. Responsible: Hans-Peter Plag, Deadline: 20 May 2004.

6 Summary of the status, deviations, and necessary actions

Hans-Peter Plag summarised the status as being acceptable. There are some serious delays which need to be delt with and brought back in line. The most severe delays are in T1.3 and T4.3. Data delivery from T4.2 is also seriously delayed. For T1.3, a new deadline of end of September was agreed for the operational page being up. For T4.3, immediate action is required.

7 Management report

7.1 Hans-Peter Plag: Presentation of the draft report

Hans-Peter Plag informed the PT that most of the partners have supplied their input and this has been compiled into a homogenous file. The main missing part is the input from most WP leaders. The WP leaders stated that they will provide the input during the meeting.

7.2 Discussion and finalising of the report (all)

The report will by finalised by the coordinator.

8 Technical Implementation Plan (TIP)

The TIP need to be implemented in the web page provided by the Commission. In order to do so, the coordinator needs to establish the project on the respective web page and to register all partners.

Action Item PT-3-10: Bente Lilja Bye to ensure that the TIP is initialised for the project and all partners are registered on the web page. Responsible: Bente Lilja Bye, Deadline: 30 June 2004.

9 External Reviewing

Hans-Peter Plag pointed out that the external reviewers so far have not been involved in the assessment of the progress. Christian Le Provost has passed away and therefore, a new expert replacing him needs to be identified.

The Project team asked Hans-Peter Plag to consider to be an external expert/reviewer.

10 The ESEAS Meetings in November 2004: Programme, web pages, invited speakers

The workshop programme was discussed in detail. During the first day, the morning session will include a 1.5 hours opening block with 30 minutes on the life and achievements of Christian Le Provost and 30 minutes on "Observing and interpretation of sea level: Where do we stand" The first 30 minutes will be available for opening addresses by the GB chair, the ESEAS-RI coordinator, a representative from Malta, the EC, IOC, ...

The last session on the last day should be separated into two blocks with last block for a summary presentation and discussions.

For all scientific sessions, there should be invited presentations and contributed presentations. It was agreed to aim for invited speakers from outside the ESEAS community while all groups contributing to the ESEAS-RI project are expected to present their results either orally or in posters. Invited speakers, though, will not be reimbursed by the workshop organisation.

For session 1, there should be at least two presentations for the test site. For the state of the art or each with respect to calibration of tide gauges, operational routines, real time data as well as directions for the future presentation, Wolfgang Scherer and David Pugh are suggested. It will be investigated whether IOC can fund the invited speaker.

For session 2, for each of the two blocks there should be an invite speaker. Suggestions were Mike Bewis for GPS co-loation and Zuhier Altamimi for reference frame. Other names brought forward were Rainer Rummel and Claude Boucher.

For session 3, Per Knudsen will find one or two invited speakers, one on future mission, and one on validation and data analysis in order to get sea level out of it.

Action Item PT-3-11: Per Knudsen to identify and invited two speakers for the altimetry session of the ESEAS Workshop. Responsible: Per Knudsen, Deadline: 15 June 2004.

For session 4, Philip Woodworth and Mikis Tsimplis were suggested.

For session 5, the names for invited presentations include Nadja Pinardi, Helge Drange, Cabanese, and Maik Thomas,. The Japanese author who produced a new data set for steric variations is also a potentially interesting speaker.

For session 6, Ben Chao is one candidate.

Action Item PT-3-12: Hans-Peter Plag to identify and invite the speakers for all sessions (except session 3) for the ESEAS Workshop. Responsible: Hans-Peter Plag, Deadline: 15 June 2004.

11 Publications

Hans-Peter Plag pointed out that publication are a major way of dissiminating the results of the project. Therefore, everybody is asked to stimulate publications from the projects.

12 Future proposals

Alan Edwards gave a brief overview of the Third Call in FP6, which is expected to be published in late June 2004. In FP6, ESEAS most likely will have to cooperate with other groups to participate in larger proposals. Within the programme "Structuring the Research Area", ESEAS may however be able to do something on its own. There is most likely only one more call within this area, which is under the horizontal activities of "Research Infrastructures", action (b).

Action Item PT-3-13: Bente Lilja Bye to check CORDIS for calls in the field of "Research Infrastructure". Responsible: Bente Lilja Bye, Deadline: 15 June 2004.

Under vertical priorities, the theme 4.2 (GMES) may be of interest, but it is not clear what will be in the 3rd Call. In order to have sea level and the ESEAS in this, the national delegates will have to be lobbying for that. The ESEAS might be in a good position since it can provide service prior to 2008 and might also be happy to have the GMES-label on it.

Another option is under priority 6.3, where there is a topic under observing system. ESEAS can be part of a proposal for the IP under 6.3.VI.1.

In the fourth call, there may be a focus on a coastal and regional seas observing system.

The ESEAS may also involve itself in a SSA under 6.3.IX. in a modified GAINS proposal.

13 The next phase of the ESEAS

13.1 The assessment report

Hans-Peter Plag informed the PT that the ESEAS is currently in the process of deciding how to continue after the Pilot Project ends in July 2004. An assessment report was requested by the ESEAS GB, (see AI GB-4-9) and the report needs to to be written by Richard Bingley and Hans-Peter Plag in the next four weeks.

13.2 Next ESEAS GB meeting

The next GB meeting needs to take place in July 2004 in order to decide on the future of the ESEAS.

13.3 Merging ESEAS and MedGLOSS

Hans-Peter Plag informed the PT that there have been new contacts between ESEAS and MedGLOSS in order to discuss a close cooperation in the future. A discussion is planned during the CIESM conference taking place early in June in Barcelona. The ESEAS-MedGLOSS meeting will take place on either 9 or 10 June 2004.

14 ESEAS/GLOSS and GMES/GEO

The ESEAS is in a strong position to be associated with and getting a role in GMES. This is due to the fact that the word Service is already in the name and the ESEAS is easily able to deliver a service before 2008.

Having associated ESEAS with GMES implies some obligations that may be difficult to meet fully because the long-term funding is not yet secured. However, the next GMES call may help here.

GMES can not be assumed to be a reasonable link to GEO for ESEAS. Alan Edwards pointed out that there has been an explotion of membership in GEO, and since this has happened, GLOSS should be there as well. This has to be discussed with Thorkild Aarup and Phil Woodworth.

Action Item PT-3-14: Hans-Peter Plag to contact Philip L. Woodworth and Torkild Aarup and to discuss membership of GLOSS in GEO. Responsible: Hans-Peter Plag, Deadline: 31 May 2004.

Per Knudsen pointed out that information management services for GMES is another aspect to be considered. Alan Edwards will send the names of potential correspondents in the IMSO (Information Management System) to Hans-Peter Plag .

Action Item PT-3-15: Alan Edwards to send the names of potential correspondents in the IMSO (Information Management System ) to Hans-Peter Plag . Responsible: Alan Edwards, Deadline: 15 June 2004.

Before Alan Edwards left, Hans-Peter Plag thanked him for the very valuable support and advice he has given to the ESEAS community and in particular the ESEAS-RI project. Alan Edwards emphasised the professionality of the ESEAS-RI project and thanked the ESEAS-RI consortium and the coordinator for their good work.

15 List of Action Items

Action Item PT-3-1: Hans-Peter Plag to ask the consortium for agreement to have Bente Lilja Bye as new coordinator. Responsible: Hans-Peter Plag, Deadline: 30 June 2004.

Status of Action Item PT-3-1: Done. Email sent out to the responsible scientists and asking to send agreement to Reidun Khalayli by 30 June 2004.
Reported on 20 May 2004 by Hans-Peter Plag.

Action Item PT-3-2: Hans-Peter Plag to inform the consortium about the requirements for documentation of human resources spend on the project. Responsible: Hans-Peter Plag, Deadline: 20 May 2004.

Rational: There are clear requirements for documentation of human resources used in the project. These need to be followed in order to avoid problems during audits.

Status of Action Item PT-3-2: Done. Email sent out to the responsible scientists with details on the required documentation.
Reported on 20 May 2004 by Hans-Peter Plag.

Action Item PT-3-3: Hans-Peter Plag to call for a Task 1.3 meeting in order to consolidate the development of the ESEAS Data Portal. Responsible: Hans-Peter Plag, Deadline: 20 May 2004.

Rational: The ESEAS Data Portal needs urgently be established and therefore, the current bottleneck due to a lack of resources at NMA needs to be eliminated. This requires input from all ESEAS-RI partners who have the right expertise. The meeting should take place in June with the goal to get the DP opeartional by September.

Status of Action Item PT-3-3: Done. Email sent out to the all ESEAS-RI members with invitation to meeting on 14 June in Copenhagen.
Reported on 20 May 2004 by Hans-Peter Plag.

Action Item PT-3-4: Hans-Peter Plag to ask the ESEAS community to provide information for the ESEAS web page "About Sea Level". Responsible: Hans-Peter Plag, Deadline: 20 May 2004.

Rational: The ESEAS web page should be an information source for sea level. Currently, very little is available of interest for non-scientific users. This is a major deficit of ESEAS, which can fairly easily be corrected.

Action Item PT-3-5: Halfdan Pascal Kierulf to provide the time series of displacement due to air pressure loading for all ESEAS CGPS sites. Responsible: Halfdan Pascal Kierulf, Deadline: 30 June 2004.

Action Item PT-3-6: Per Knudsen together with Hans-Peter Plag to organise a Task 3.3 meeting in June in order to assess the results of T3.1 and T3.2 and to decide how to solve T3.3. Responsible: Per Knudsen, Deadline: 20 May 2004.

Status of Action Item PT-3-6: Done. Email sent out to the all ESEAS-RI members with invitation to meeting on 15 June in Copenhagen.
Reported on 20 May 2004 by Hans-Peter Plag.

Action Item PT-3-7: Per Knudsen to clarify whether Mikis Tsimplis can take the leadership for T3.4. Responsible: Per Knudsen, Deadline: 20 May 2004.

Action Item PT-3-8: Hans-Peter Plag to contact Maria-Jesus Garcia and to clarify the status of the CGPS receiver, which is supposed to deliver data since early April. Responsible: Hans-Peter Plag, Deadline: 20 May 2004.

Action Item PT-3-9: Hans-Peter Plag to contact all partners with pending CGPS installation and to urge them to progress as soon as possible since otherwise their installation may not be useable for ESEAS-RI. Responsible: Hans-Peter Plag, Deadline: 20 May 2004.

Action Item PT-3-10: Bente Lilja Bye to ensure that the TIP is initialised for the project and all partners are registered on the web page. Responsible: Bente Lilja Bye, Deadline: 30 June 2004.

Action Item PT-3-11: Per Knudsen to identify and invited two speakers for the altimetry session of the ESEAS Workshop. Responsible: Per Knudsen, Deadline: 15 June 2004.

Action Item PT-3-12: Hans-Peter Plag to identify and invite the speakers for all sessions (except session 3) for the ESEAS Workshop. Responsible: Hans-Peter Plag, Deadline: 15 June 2004.

Action Item PT-3-13: Bente Lilja Bye to check CORDIS for calls in the field of "Research Infrastructure". Responsible: Bente Lilja Bye, Deadline: 15 June 2004.

Action Item PT-3-14: Hans-Peter Plag to contact Philip L. Woodworth and Torkild Aarup and to discuss membership of GLOSS in GEO. Responsible: Hans-Peter Plag, Deadline: 31 May 2004.

Action Item PT-3-15: Alan Edwards to send the names of potential correspondents in the IMSO (Information Management System ) to Hans-Peter Plag . Responsible: Alan Edwards, Deadline: 15 June 2004.

Action Item PT-3-16: Lesley J. Rickards to ensure that the quality control document is finalised and made available on the delivery page. Responsible: Lesley J. Rickards, Deadline: 30 June 2004.

Rational: According to AI PT-2-3, the document was supposed to be available in Nov. 2003. It now needs to be made available a.s.a.p.

Action Item PT-3-17: Lesley J. Rickards to ensure together with the T1.2 members and the whole ESEAS consortium that a standard ESEAS Quality Control software is defined and that the programs are made available for down-load on the ESEAS Web server. Responsible: Lesley J. Rickards, Deadline: 30 June 2004.

Rational: A standard software package for quality control compliant to the quality control document is a necessary step towards a homogeneous ESEAS data quality. Initially, the software is made available for down-load. However, a next step should be to have the software installed on the ESEAS Data Server.

16 Any Other Business (AOB)

There was no other business.

17 Date and place of next meeting

The next PT meeting will be held subsequent to the ESEAS Workshop on November 4, 2004 in Malta.

End of Minutes